Reportedly, the
availability of the Kiev-based Podolsky bridge across the Dnieper River
accounts for more than 80%, whereas the municipal administration
estimates it at 65%.
As expected, workers will connect all the
joints of the arch and hang the bridge by cables by this year-end.
Large-scale work will be done on the Rybalsky peninsula, where between
150 and 230 bridgebuilders will work in two shifts.
Plans are in
hand to complete the installation of reinforcing structures of the
bridge next year, as well as to weld the joints of the arch and
disassemble temporary supports. Experts say that although these supports
look "somewhat fatigued" and rusty, they are strong enough and 100%
failure-proof. Currently, professionals of the Paton Electric Welding
Institute are monitoring their condition.